Drax Development Underway

Drax Development Underway

We are pleased to announce that planning permission has been passed for 14 executive, 4 bedroom detached homes at our Drax development. Demolition on the site is currently underway with groundwork’s due to start in 2 weeks time with the first homes due to be completed later this...
Only 1 Terrace House remaining at our Howden Site

Only 1 Terrace House remaining at our Howden Site

The High Bridge Phase One part of our development in the centre of Howden is well on the way to being completed. Four of the five terrace homes have been sold leaving only one remaining. Phase Two of the development is progressing well with the detached property now up to roof height and waiting for it’s phase 1 fit out. If you are interested in the remaining terrace home or our detached property, please contact our sales team on 01405 819 144 or email:...

Planning Permission granted at Drax site

We are pleased to announce that planning permission has been passed for 14 executive, 4 bedroom detached homes at our Drax development. The site is currently being prepared ready to start the groundwork’s in 2 weeks time with the first homes due to be completed later this...
Roof going on 5 Mews Houses

Roof going on 5 Mews Houses

Progress over the past month has seen the block and brick work now complete on the 5 Willow Mews Houses. The Roof timbers are in place and the roof is due to be tiled and finished in the coming...

5 Mews houses at first floor level

April saw our brick layering team get up to the first floor level on the 5 Mews houses. The scaffolding has just been erected and we plan to be up to roof level within the next week and hope to be water tight and read for first fix by mid...

Howden site cleared and development commences

After receiving the go ahead to start the development from the planning department in January, we now have the development well underway. We have started by clearing the site to make way for essential ground works including drainage, water, electricity and the foundations for the 5 south facing dwellings which face onto Hailgate. We plan to have all the amenities and foundations in place by the end of...